Monday, November 19, 2012

Drywall

Hanging drywall.

The drywallers hung sheetrock in three days.  We're waiting for the tapers and finishers.

Boiler

Boiler fully connected to 4 main zones plus the domestic hot water heater (extreme right).
The boiler was finally plumbed and commissioned.  We lost a week while the plumber went hunting (fortunately he didn't hurt himself) but got the system up and running just in time for the weather to turn cold.

Monday, October 8, 2012

In Floor Heat

Some of the tubes have been installed to carry hot water into the floor.  The tubes will be covered with 1 1/2 inches of concrete (then a finished floor is applied).
Heating tubes in the master bath

Heating tubes in the master closet.

Utilities

Gas line and flue connected to the boiler.

Nearly all the circuits have been connected to the circuit breakers.  There are regular breakers, ground fault and now arc fault breakers ($$$$$).





 
The high efficiency boiler is almost ready to be connected, and the electrical panel almost finished.

Ready for stain

Washed and ready for staining.
The house has been power washed in preperation for staining, windows are being masked.

Gas

Gas line in the trench.

Kevin from the gas company installs the regulator/meter.  We'll be connected in a few days.
The gas piping has been installed (will be inspected in 2 days).  Now a ditch has been excavated to run the gas and electric lines from the street.

Thursday, September 27, 2012

Siding

The back side of gthe garage

The front of the house.  Log, Board and batten and windows.
Board and .  It looks great, and will be stained along with the logs.Batten siding is installed to non-log exterior walls